Humanists for Social Justice and Environmental Action supports Human Rights, Social and Economic Justice, Environmental Activism and Planetary Ethics in North America & Globally, with particular reference to the Universal Declaration of Human Rights and other Human Rights UN treaties and conventions listed above.

Tuesday

Green groups appeal Alberta power plant ruling

Green groups appeal Alberta power plant ruling
Environmental groups have launched a court action against Alberta's utility regulator, arguing it fast-tracked its approval of a coal-fired power plant so the operator could avoid upcoming carbon regulations.

Ecojustice and the Pembina Institute said on Tuesday they seek to appeal the Alberta Utilities Commission's June 30 interim decision granting Maxim Power Corp approval to build a 500-megawatt generating unit near Grand Cache in western Alberta.

The green groups said they aim to show the commission rushed its decision without considering all the evidence, as it did not conduct a public hearing.

It pointed out the AUC granted Maxim's request to get the green light by June 30, the latest date allowing the plant to be built by July 1, 2015. The company had said it received assurances from the federal environment minister that it could avoid new carbon rules if the plant was built by then.

'It's as if getting this project approved in advance of the federal coal regulations is somehow in the public interest,' said Chris Severson-Baker, Pembina's managing director.

'It's really bizarre, not even having a hearing, not granting standing to appear before the AUC to groups like the Pembina Institute who have been working on these issues regarding coal-fired power plants for decades.'